Water Line Installation 3/22/24 – 4/5/24

Water Line Installation 3/22/24 – 4/5/24

K. Barnett and Sons is continuing work that will affect traffic in your neighborhood soon.

As part of the Clovis Re-Use water project, we will be installing a water line that affects traffic in your area. We will be impacting, Echols Avenue, Golden Street,
and Sandia Drive. Please see the attached map. We plan to begin work Friday, 3/22/24 and anticipate work to last about 2 weeks until 4/5/24.

Please follow signage. There will be “Road Closed to Thru Traffic” signs. We will do our best to ensure access to local traffic. Please do not park any vehicles on the
street during this time. Any vehicles left in the way of construction may be towed. I realize this is going to be inconvenient and can assure you that we will do our
best to get this work complete as fast as we can during civilized hours. If you have any questions or specific concerns, please don’t hesitate to contact us
at: 575-762-4407.

Download the PSA, here.

Sandia-Media-Release-3.18.24