Title 12 STREET, SIDEWALKS AND PUBLIC PLACES*
Chapter 12.06 STREET, ALLEY AND RIGHT-OF-WAY EXCAVATIONS
12.06.100 Backfill requirements.
A. All excavations for which a permit has been issued shall be inspected
prior to the replacement of any material. The public works department shall
determine whether additional inspections are necessary during the filling and
compaction of any excavation. All excavation shall be filled with no more than
eight-inch lifts and shall be compacted with a tamper, roller, or approved
compactor. No wheel rolling will be allowed.
B. All backfill material in the
trench shall be thoroughly compacted to a minimum of ninety percent of the
maximum density throughout as determined by ASTM D-1557, except that the top six
inches of sub-grade material in local residential streets, and the top twelve
inches of sub-grade material in arterial streets, shall be compacted to a
minimum of ninety-five percent maximum density unless the backfill or sub-grade
material contains thirty-five percent or more material passing the number two
hundred sieve, in which the compaction shall not be less than ninety percent of
maximum density. The moisture content of the backfill material shall not be more
than three percent nor less than two percent of the optimum. The obtaining of
the correct moisture content will be the responsibility of the applicant.
Moisture and density requirements shall be governed by ASTM D-1557. The
classification of the backfill required shall be shown in the application for
the excavation permit.
C. Failed excavations shall be the responsibility of
the applicant for one year after the excavation, and all such failed excavations
shall be repaired within ten days after failure. Should any failed excavation
not be repaired by the responsible applicant, the city may repair the excavation
and charge the costs to the applicant.
D. When an excavation has been cut
through existing pavement, the compaction for the top six inches or twelve
inches, whichever may be the case, means the six inches or twelve inches of
material placed immediately below the bottom or base of the existing pavement
slab. The remainder of the backfill up to the top of the existing pavement
surface is to be compacted sufficiently to provide a level and safe riding
surface and maintained in that condition by the applicant until the permanent
pavement patch can be installed. Pavement patches must be installed within ten
days after completion of the backfill unless a longer period may be required by
extreme weather conditions.
E. When existing asphalt has been disturbed, or
when asphalt is to be placed on the street, tack oil will be required on all
asphalt edges. Only hot asphalt is allowed, cold-mix can only be utilized for
temporary patches until hot asphalt application can be completed.
F. In no
event shall concrete or asphalt be applied to any street until the public work
director or his designee has approved all sub-grade preparations.
G. The
director is authorized to make or have made backfill moisture/density tests for
the purpose of determining compliance with the compaction requirements of this
section. Tests will not exceed one eight-inch lift per block of trench unless
failures indicate the need for additional tests. Such tests are to be made in
accordance with the Standard Procedures of the American Standards for Testing
and Materials, including the latest revisions thereto. All costs connected with
required testing will be made at the expense of the applicant.
H. In the
event the completed backfill fails to meet the density requirements of this
section when tested, the director shall order the faulty backfill material
removed, replaced and recompacted to the required density specified by this
chapter, and may retest the backfill, all at the applicant’s expense.
(Ord. 1583-98 § 3(part), 1998).
<< previous | next >>