Norris Street Roadway Improvement Project

Norris Street Roadway Improvement Project

On February 21, 2013, the Clovis City Commission awarded the project to K. Barnett & Sons, Inc., for $3,966,809.98.  The proposed project will include roadway improvements, bike lanes, sidewalks, and storm drain.  The first phase of the project is currently underway from Mollie Circle to Wilthite Road and also includes the construction of a drainage ditch from Norris St. to a playa lake located to the east.  The first phase is scheduled to last until August.  The second phase of the project will be from Mollie Circle to Llano Estacado Blvd. and is scheduled from August to February 2014.  During construction please adhere to all construction signs and seek an alternate route when possible.  Should you have any questions please contact Justin Howalt, City Engineer, at jhowalt@cityofclovis.org.